Summary Information
- Ownership: Novatek / Total
- Website: http://www.novatek.ru/
- Location: Yamal Peninsula, Russia
- Capacity: 15-16 million tons/annum
- Status: Planned
Brief Description
- A very large gas liquifaction plant. Currently the capacity has not been decided
Technical Details
- Storage capacity:
- Constructor:
- CB&I to provide front end engineering & design (FEED) services
- Licensor:
Ongoing Projects/Project Status
- The FEED contract is scheduled for completion in the first half of 2011
Suppliers / Customers
- Suppliers: Gas will come from the South Tambeyskoye Gas Field
- Customers:
History
- 2011 - Total becomes partner in the project
- 2011 - CB&I selected to provide front end engineering & design (FEED) services
- 2011 - NOVATEK announced that it has executed a call option agreement for the right to purchase the remaining 25.1% stake in Yamal LNG for USD 526 million
Other Information
- -
Relevant Links
- CB&I Awarded Concept Development for Yamal LNG Project, May 04, 2010
- Gazprom and NOVATEK sign cooperation agreement for LNG production in Yamal peninsula
- Russia: Total enters into a strategic partnership with the independent gas company Novatek
- CB&I Awarded Feed Contract for Yamal LNG Liquefaction Plant
- NOVATEK purchases option in Yamal LNG
- NOVATEK increases stake in Yamal LNG
page revision: 9, last edited: 03 Oct 2011 11:34