Ugandan Government Refinery Project

Summary Information

  • Ownership: Ugandan State / Private Partners
  • Website:
  • Location: Kabale in Hoima, Uganda
  • Capacity: 1.0 million tons/annum & 20,000 bbl/day
  • Nelson Complexity:
  • Project Stage: Feasibility (Dec 2009)
  • Expected Completion: 2015

The Project

  • Project Type: Greenfield Refinery
  • Project Summary: The refinery will be built in phases, first 20,000 bpd, then expanded to 60,000 bpd
  • Main Contractors
    • Foster Wheeler undertook a feasibility study

Refining Units

  • -

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • The project will use Ugandan sweet, waxy crude which has low sulphur under 0.5 percent per weight

Products Produced

  • The refinery will produce mainly gasoline & middle distillates

History

  • 2010 - Foster Wheeler awarded feasibility study
  • 2011 - Budget but aside for project

Other Information

  • The nature of the local crude production and the location far from any port, means that Uganda needs to build a refinery to fully exploit its crude oil production.
  • The crude produced is waxy, and needs a heated pipeline to stop it freezing.

Relevant Links

Page tags: refinery uganda
Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License