- La Plata Refinery - Catalytic Cracking Revamp Project
- Repsol - YPF
- Summary: Replacement of Reactor Cyclones, Increment Residue Processing Capacity, Increment Air Consumption for Burners, lift and fluffing, Upgrades in FCC Fractionation Train
- Schedule: September 2006 – February 2008 (17 months)
- Scope: Basic Engineering Verification, Detail Engineering, Procurement, Fabrication, Construction, Commissioning, Start Up Assistance
- La Plata Refinery - Coker Unit Revamping
- Repsol - YPF
- Summary: Processing Capacity: 185 m3,/h, Coke Storage Capacity: 12,500 ton,
- Schedule: December 2007 – October 2008 (10 months)
- Scope: FW Package Consistency Check Analysis, FEL 3 Coker Island, Basic Design & FEL 3 Off Sites, Basic Design & FEL 3 Coke Storage and Handling System, Fractionation and Gas Concentration, Systems Debottlenecking Study.
- Barrancabaermeja Santander Refinery - Consolidated Operations Center **
- Ecopetrol
- Summary:** The main objective is to have an unified control room for the whole refinery.
- Scope: EPC contract, Detail engineering, Procurement, Construction, Commissioning and start up
- La Plata Refinery - FCC Gasoline Splitter
- Repsol - YPF
- Summary: Processing Capacity: 4,800 m3/d (30,200 bpd)
- Schedule: June 2004 – November 2005 (Phase 1: 18 months), June 2005 – May 2006 (Phase 2: 12 months)
- Scope: Basic Engineering Completion, Detailed Engineering, Procurement, Fabrication, Site Erection, Commissioning, Start Up Assistance
- Refinery Process Scheme Study
- Lujan De Cuyo Refinery - Splitter Unit
- YPF
- Summary: FCC Naphtha Capacity: 60 m3/h (9060 bpd), Produce new cut points for HDS unit,
- Schedule: September 2005 – December 2006 (15 months)
- Scope: Basic Engineering Verification, Detail Engineering, Procurement Instruments & Pumps, Precommissioning & Commissioning Assistance, Start Up Assistance
- Salamanca Refinery - Sulfur Recovery Unit
- Pemex
- Summary: Capacity: Sulfur recovery: 80 tn/day,
- Schedule: Project award: March 2010, Start up: December 2012
- Scope: Detail engineering, Management, Procurement, Fabrication, Transports, Construction, Precommissioning & commissioning,Start up
- Block 16 Oil Fields - Topping & Diesel Production Unit
- Repsol
- Summary: Heavy Crude Oil Production: 8,000 bpd
- Schedule: December 1998
- Scope: Basic & Detailed Engineering, Procurement, Construction, Erection, Commissioning & Precomissioning, Start Up & Test Run, Operation & Maintenance, BOT project
- Topping & Diesel Production Unit - Cerro Dragón
- San Lorenzo Refinery - Topping & Vacuum Fired Heaters
- Petrobras
- Summary: Three Fired Heaters for Topping Distillation Units I, II & III. & One Fired Heater for Vacuum Distillation
- Schedule: July 2005 – December 2006 (17 months)
- **Scope: ** Engineering, Procurement, Fabrication, Construction, Commissioning, Start Up Assistance