Swinoujscie Polskie Lng Terminal
Summary Information
- Ownership: Polskie Lng
- Website: http://en.polskielng.pl/
- Location: Swinoujscie
- Capacity: million tons/annum
- Status: Planned
Brief Description
- The facility is the first such installation in central Europe
Technical Details
- Storage capacity: Two LNG storage tanks, each with a capacity of 160,000 cubic metres
- Unloading capacity: Tankers with a capacity of up to 216,000 m³
- Send out capacity: 5 bn m³ of natural gas annually
- Constructor:
- Feasibility Study performed by an international consortium, including ILF
- The terminal was designed by Canadian SNC Lavalin Services Ltd.
- The General Contractor of the project is a Polish-Italian consortium Saipem – Techint – PBG
- The project is supervised by British Atkins Ltd.
- Licensor:
Ongoing Projects/Project Status
- The LNG terminal is due to open in 2014
Suppliers / Customers
- Suppliers:
- Customers: Polish domestic consumption. The grid is to be supplied by a new gas pipeline on the Świnoujście-Szczecin route with a diameter of 800 mm and approx. 80 km in length
History
- 2006 - Feasibility report awarded
- 2010 - The project received financial support from the EU
- 2011 - The EIB signs a loan agreement for the project
- 2011 - GAZ-SYSTEM S.A. signed an agreement for the construction of the Świnoujście-Szczecin gas pipeline
Other Information
- Up to 310 million (€ 80 million) in funding will come from the EU
- The European Investment Bank (EIB) will provide 600 mln PLN
Relevant Links
- The deal with the LNG terminal contractor signed
- Exiting the economic crisis together
- Construction of Polish LNG terminal closer
- Atkins energy contract win in Poland - 10 June 2010
- Techint Italy Wins the Bid with Saipem and PBG For The Regasification Terminal in Poland Under 2010 press releases
- Saipem: Board of Directors approves six-month report at June 30, 2010
- Poland moves in new directions regarding Liquid Natural Gas Import
- GAZ-SYSTEM S.A. OBTAINED A LOAN FROM THE EIB FOR THE CONSTRUCTION OF THE LNG TERMINAL IN ŚWINOUJŚCIE
- GAZ-SYSTEM S.A. signed an agreement for the construction of the Świnoujście-Szczecin gas pipeline