Stella Oil And Gas Field

Related Pages

UK Oil & Gas Fields

Ithaca Oil & Gas Fields

Upstream News

{"module":"feed\/FeedModule","params":{"src":"http:\/\/killajoules.wikidot.com\/feed\/pages\/pagename\/blog%3A_start\/category\/blog\/tags\/Upstream\/limit\/10\/t\/My+Blog","limit":"5","module_body":"* %%linked_title%%"}}

For More Upstream News



Summary Information

  • Operator: Ithaca
  • Country: UK
  • Location: central North Sea
  • Production start: 2017
  • Partners:
  • Type: Oil & Gas
  • Estimated Reserves:
  • Production Volume:

Description

  • The Greater Stella Area lies within United Kingdom Continental Shelf (UKCS) Block 30/06a, in the central North Sea. Block 30/06a is approximately 238km south east of Peterhead and 17km from the UK-Norway median line
  • The development includes the Stella, Harrier and Hurricane fields
  • The development scheme is likely to involve up to 5 production wells drilled from a sub-sea drilling centre on Stella and 2 further production wells drilled on Harrier. The Harrier centre will be tied back to the Stella where the hydrocarbons from both fields (oil and gas) will be combined
  • The development solution will involve the use of the FPF-1 semi-submersible floating production unit, owned by Petrofac
  • Gas is transported on the Central Area Transmission System ("CATS") to the Teesside Gas Processing Plant TGPP
  • The Vorlich field is being developed as an extension of the Stella develoment. Vorlich is a two-well development which will be tied back to the FPF-1 floating production facility

Contractors

  • EPC Subsea: Manufacture of drill centre manifolds, riser base structures and export pipeline tie in structures
  • Technip: EPIC subsea contract
    • Detailed design and pipelay of a 33 kilometre 10” oil export and 63 kilometer 10” gas export pipeline to the production platform,
    • Various subsea works to the Stella main drill center and North drill center including;
    • Installation of manifolds, tee structures, flexible pipelay and spoolpiece components,
    • Installation of the mooring system to the production platform and design and installation of five-slot mid water arch.
  • Vallourec: Provision of seamless linepipe including coating and welding services
  • Applied Drilling Technology International: Manage development drilling and completion operations

Vorlich field

  • WorleyParsons: front-end engineering design (FEED) for the subsea tieback

History

  • 2011 - Ithaca award EPC Subsea Facilities Management Contract
  • 2012 - Field development approval awarded
  • 2012 - Technip awarded an EPIC subsea contract
  • 2017 - First hydrocarbons produced
  • 2018 - Approval granted for the Vorlich development

Geology

  • Palaeocene Andrew sandstone reservoir

Links

  1. Greater Stella Area Development Concept Selected
  2. Ithaca award EPC Subsea Facilities Management Contract
  3. Technip awarded substantial UK North Sea contract
  4. Vallourec provides Technip with integrated solutions for an Offshore Project in the Central North Sea
  5. Greater Stella Area Development Update
  6. Greater Stella Area Turnkey Drilling Contract
  7. Major milestone in the Greater Area Stella Development Achieved
  8. Successful Stella A2 Well Test Results and GSA Development Update
  9. Greater Stella Area Update
  10. Ithaca Energy successfully completes flow test operations on Stella A3 well
  11. Stella First Hydrocarbons
  12. BP receives OGA approval to develop Vorlich field in North Sea
  13. WorleyParsons awarded Ithaca’s Vorlich FEED