Sines LNG Terminal
Summary Information
- Ownership: REN Atlântico
- Website: http://www.ren.pt/
- Location: Sines, Portugal
- Capacity: 6.0 million tons/annum
- Status: In Operation
Brief Description
- The LNG terminal consists of a docking station with a discharge capacity of 40,000 cubic meters to 165,000 cubic meters with an average discharge time of 20 hours, two storage tanks each having a capacity of 115,000 cubic meters and five open rack vaporizers for regasification.
Technical Details
- Storage capacity: Two storage tanks each having a capacity of 115,000 cubic meters
- Unloading capacity:
- Send out capacity: The LNG terminal has a guaranteed (nominal) send out capacity of 600,000 cubic meters per hour (5.26 bcm per year), with a peak (interruptible) capacity of 900,000 cubic meters per hour
- Constructor:
- Tractebel
- Complete EPC turnkey project for the initial construction
- FEED and ITB package for the expansion project
- Tractebel
Ongoing Projects/Project Status
- The terminal is undergoing an expansion by SMM increasing the plant's receiving capacity from 6 million to 9 million metric tons of LNG per year.
- Increased regasification capacity from 900,000 nm³/h to 1,350,000 nm³/h
- Storage capacity of the terminal will be increased from 240,000 m³ to 390,000 m³ with the mechanical construction of one LNG tank with 150.000 m3 of capacity.
- The cost of the project is expected to be about $265 million, and completion is set for 2012
Suppliers / Customers
- Suppliers:
- Customers: The LNG terminal was set up as a tolling facility, charging customers handling fees
- EDP has a contract to purchase LNG from the Corpus Christi LNG Export Terminal Project
History
- 2000 - Tractebel awarded EPC contract
- 2004 - Terminal Commissioned
- 2006 - Terminal acquired by REN
- 2008 - Expansion project launched
- 2009 - EPC contract for expansion project awarded
- 2012 - Expansion project completed
Other Information
- -
Relevant Links
- Tractebel Engineering LNG References
- Terminal Webpage
- SINES LNG Terminal: low cost/ fast track project but new technologies and an answer to EN 1473 new safety approach
- Sines LNG Terminal Expansion Project
- EPC Contractor Awarded for LNG Terminal Expansion in Sines, Portugal
- PROJECT FINANCING OF A LNG IMPORT TERMINAL AS A TOLLING FACILITY
- Contract Signed for Expansion of GNL Sines Terminal
- JC Carter Delivers Eight Third Generation, High-Efficiency Pumps to Sines, Portugal LNG Terminal Expansion
- SMM concluded a project at the Liquefied Natural Gas (LNG) REN Terminal, in Sines
- Ren Completes Expansion Project Of The Sines LNG Terminal
- Cheniere and EDP Sign 20-Year LNG Sale and Purchase Agreement
page revision: 17, last edited: 26 Dec 2014 13:42