Summary Information
- Ownership: Shannon LNG (Hess)
- Website: http://www.shannonlngplanning.ie/
- Location: Shannon Estuary, County Kerry, Ireland
- Capacity: million tons/annum
- Status: Planned
Brief Description
- -
Technical Details
- Storage capacity: 2* 200,000 m3 tanks
- Unloading capacity:
- Send out capacity:
- Constructor: CB&I was awarded a pre-FEED contract
- Licensor:
Ongoing Projects/Project Status
- The project is currently held up over issues relating to the costs of the inter-connector. All market participants are currently required to pay their share of the costs. However, as Shannon LNG will not actually use it, they have applied for a waiver
Suppliers / Customers
- Suppliers:
- Customers: Shannon LNG Limited proposes to construct a natural gas pipeline from the LNG terminal, to connect with the national gas grid approximately 26 kilometres east near Foynes, County Limerick.
History
- 2007 - Planning application submitted
- 2008 - The project received planning permission under the Strategic Infrastructure Act from An Bord Pleanála
- 2009 - CB&I was awarded a pre-FEED contract
Other Information
- -
Relevant Links
- Shannon LNG Booklet
- Arup, Shannon LNG Terminal, Shannon Estuary, County Kerry
- Shannon Pipeline
- Shannon LNG - Exemption Order from Regulated Third Party Access
- AWARD Contract notice - Utilities