Probably the most exciting project in the world of Oil & Gas. The platform will be the largest ship ever built
Introduction
- The Company is EPC Contractor and are supplying Lump Sum Turn-Key Projects
- PROKOP ENGINEERING Brno was founded in 1990 and from the very beginning has been able to follow up the long tradition in Brno regarding supplying turn-key projects in the construction of industrial plants, especially in the fields of processing crude oil and oil products and gas processing.
References
- Dukan Refinery
- Iraq
- Technoexport - KAT
- CRUDE DISTAILLATION UNIT - 20 000 BPSD
- Commissioning planned for 2013
- Paramo Pardubice Refinery
- Czech Republic
- Upgrade of Ultra - Low Sulfur Diesel HDS Unit - Phase II
- Commissioned 2011
- Litvinov Refinery
- Czech Republic
- Revamp Of MEA Unit
- Commissioned 2011
- Paramo Pardubice Refinery
- Czech Republic
- PARAMO
- Upgrade of Ultra - Low Sulfur Diesel HDS Unit - Phase I
- Commissioned 2010
- Paramo Pardubice Refinery
- Czech Republic
- PARAMO
- White Spirits / Gasolines
- Commissioning 2010
- Basrah Refinery
- Iraq
- Technoexport - South Refineries Co
- CRUDE DISTILLATION UNIT + LPG Unit 70 000 BPSD
- Commissioning 2012
- Puralube
- Germany
- HyLube 2 Heaters Pckg
- Commissioning 2008
- Daurah Refinery
- Iraq
- Technoexport - Midland Refineries Co.
- CRUDE DISTILLATION UNIT 2 - 70 000 BPSD
- Commissioning 2010
- Litvinov Refinery
- Czech Republic
- Amine Treating Unit MEA / Revamp
- 60 t/h
- Commissioning 2007
- Brest Refinery
- Belorussia
- Ultra Low Sulfur Diesel HDS - 70 000 t/y
- Albemarle / UOP
- Commissioning planned for 2012
- Bulgarian Petroleum Refinery
- Bulgaria
- Crude/Vacuum Distillation Unit, Ultra Low Sulfur Diesel HDS Unit Reformer, Isomerizer - 100 000 t/y CDU
- Feasibility Study - PE and various licensors
- Completed 2006
- Litvinov Refinery
- Czech Republic
- Revamp Visbreaking Unit
- 104 t/h
- Commissioning 2007
- Daurah Refinery
- Iraq
- Technoexport - Midland Refineries Co.
- CRUDE DISTILLATION UNIT 1 - 70 000 BPSD
- Commissioning 2009
- Banias Refinery
- Syria
- VACUUM DISTILLATION UNIT, Deep overhaul 3 000 000 t/y
- Beicip Franlab
- Technoexport / Banias Refinery Co.
- Commissioning 2007
- Paramo Pardubice Refinery
- Czech Republic
- ULTRA LOW SULFUR DIESEL / HDS SR Middist. Diesel Oil upgrade
- 300 000 t/y - AXENS
- In operation since 2005
- Slovnaft Bratislava Refinery
- Slovakia
- Railway Tanks Cleaning Plant
- 40 tanks/day
- Commissioning planned for 2007
- Kralupy Refinery
- Czech Republic
- LPG Separtion
- 10 t/hr
- In operation since 2005
- Litvinov Refinery
- Czech Republic
- Sulfur Recovery Unit/Revamp, incl. Sulfreen Unit, Claus IV, Claus III, Claus II
- 150 t/d
- In operation since 2004
- Slovnaft Bratislava Refinery
- Slovakia
- Hydrodesulphurization of Middle distillates
- 50 000 t/y Albermarle (AKZO NOBEL)
- Detail Design and Engineering completed
- Lube Plant
- Egypt
- Lube Oil Re-refining Plant - complex of units incl. Lube Oil Blending 25 000 t/y
- UOP, KOCH, MISR CANADA
- 2009
- Lube Plant
- Germany
- IAB PURALUBE
- Hylube Process Plant 80 000 t/y
- UOP / IAB
- In operation since 2004
- Banias Refinery
- Syria
- Banias Refinery Co.
- Crude Distillation Unit / Revamp 6 000 000 t/y
- IPIP
- In operation since 2003
- Litvinov Refinery
- Czech Republic
- Sour Water Stripper / Revamp
- Increase from 24 t/h for 35 t/h
- In operation since 2003
- Litvinov Refinery
- Czech Republic
- Bitumen Blowing Unit/Revamp
- 8 000 Nm3/h (gas consumption)
- In operation since 2002
- Litvinov Refinery
- Czech Republic
- Crude Distillation - Vacuum Distillation Unit / Revamp
- 1 800 000 t/y
- In operation since 2003
- Slovnaft Bratislava Refinery
- Slovakia
- Crude Distillation - Vacuum Distillation Unit
- 159 000 t/y
- In operation since 2001
- Litvinov Refinery
- Czech Republic
- Naphtha Splitter / Revamp
- 800 000 t/y
- In operation since 2002
- Kralupy Refinery
- Czech Republic
- Fluid Catalytic Cracking-ISBL Project(incl. Elevated Flare, Cooling Towers etc.)
- 1 311 000 t/y UOP UOP, ABB / Fluor Daniel, PROKOP ENGINEERING
- In operation since 2001
- Paramo Pardubice Refinery
- Czech Republic
- Hydrodewaxing - Hydrofinishing
- 10 t/hr - IFP
- First stage Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Hydrorefining of Lube oil Distillation
- 25 t/hr IFP
- First stage Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Production of V.H.V.I. Base Oils
- 50000 - 55000 t/y IFP
- First stage Engineering completed
- Lube Plant
- Egypt
- DCH/Hylube Process Unit 25 000 t/y
- UOP
- Paramo Pardubice Refinery
- Czech Republic
- Isomerization C5/C6
- 6,6 t/hr - IFP
- Basic Engineering & Detail Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Reforming Unit
- 18,4 t/hr - IFP
- Basic Engineering & Detail Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Naphtha Hydrotreater
- 38 t/hr - IFP
- Basic Engineering & Detail Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Gasoline Complex(incl. Elevated Flare)
- 200 000 t/y - IFP
- Basic Engineering & Detail Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- LPG Unit 154 640 t/y
- In operation since 1999
- Lube Plant
- Arzerbaijan
- Lube Oil Blending and Packaging Complex - 5000 t/y
- Process, Mechanical and Control/Instrumental Part
- Detail Design completed; Execution interrupted
- Railway Tank Cleaning
- Russia - Jaroslavl
- 180 - 210 tanks/24 hrs
- Detail Design completed; Execution interrupted
- Paramo Pardubice Refinery
- Czech Republic
- Lube Oil HY - Finishing
- 20000 - 60000 t/y - IFP
- First stage Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Furfural Treating 100 000 t/y
- EDELEANU EDEL
- First stage Engineering completed
- Paramo Pardubice Refinery
- Czech Republic
- Vacuum Distillation Unit (Lube Cuts)
- 960 t/day of AD residuum
- In operation since 1997
- Paramo Pardubice Refinery
- Czech Republic
- Elevated Flare
- 7000-14000 kg/hr off gases
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- Sour Water Stripping
- 2,2 m3/hr
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- SRU incl. TGCU (RAR)Sulphur Recovery Unit / Tail GAS Clean Up
- 90-400 kg S/hr Technip KTI,SHELL
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- MDEA - Treating of Acid Gases
- 100-440 Nm3 H2S/hr
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- H2 - Steam Reforming of NG (CH4)
- 1580 Nm3/hr Technip KTI & UOP (PSA)
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- HDS SR Middist. Diesel Oil
- 250 000 t/y Based on AKZO NOBEL catalyst
- In operation since 1996 / 1997
- Paramo Pardubice Refinery
- Czech Republic
- Plant Complex HDS SR Middist. incl. Off Site Facilities
- 250 000 t/y
- In operation since 1996 / 1997
- Lube Plant
- Czech Republic
- Lube Oil Blending and Dispatching - 60000 t/y
- EUB
- KORAMO
- In operation since 1997
- Paramo Pardubice Refinery
- Czech Republic
- Lube Oil Blending and Dispatching
- 40000 t/y
- In operation since 1994
- Paramo Pardubice Refinery
- Czech Republic
- Bitumen-Bentonite Suspensions
- 5 t/hr
- In operation since 1993