Prelude Floating LNG Terminal

14737949310_3b4bde1eee_m.jpg

Probably the most exciting project in the world of Oil & Gas. The platform will be the largest ship ever built


Introduction

  • Micoperi has decades of experience in installing structures offshore in all conditions and in providing technical solutions to complex problems. The two main vessels, the M30 and the Seminole both have the capability to install offshore structures, jackets, topsides, modules etc.
  • The Company has all the skills and equipment in-house to perform most installation projects without the need for third parties and has the experience to take on a full EPIC contract including the engineering and fabrication in accordance with the clients’ requirements.

Experience

  • Note:
    • IE = Installation Engineering - P = Procurement - F= Fabrication - I= Installation - H= Hook-up - D= Demolition - T= Transportation SI = Subsea Installation C= Commissioning
  1. Tuna Gas Field
    • Offshore Egypt
    • PETROBEL
    • Tuna platform transportation and installation
    • 2010
    • IEPTI
  2. PETROBEL/PMS - PFSE2-BIS deck installation and shallow diver works; PFSE2-BIS transportation and installation and PFSE2 production and 10” riser replacement - Offshore Egypt - 2010 - EITISI
  3. Temsah Gas Field
    • Egypt -Offshore
    • PETROBEL/PMS
    • Temsah Gas PLEM Replacement – Preliminary Activities, Lifting Activities, Reconnection and Start-Up Operations
    • 2009
    • IEPTI
  4. North Bardawil Gas Field
    • Egypt
    • PETROBEL/PMS
    • North Bardawil 14” Closing Spool Installation
    • 2009
    • IEPTI
  5. Temsah Gas Field
    • Egypt -Offshore
    • PETROBEL/PMS
    • Temsah-4 Vibro Hammering Services, Temsah-4 ptf.
    • 2009
    • IEPTI
  6. Temsah Gas Field
    • Egypt -Offshore
    • PETROBEL/PMS
    • SSIV 32”/24” Valve Skid Off-shore Transportation & Installation
    • 2008
    • IEPTI
  7. North Bardawil Gas Field
    • Egypt - Offshore
    • PETROBEL/PMS
    • North Bardawil Riser & J-tubes offshore Transportation & Installation & Barboni-1 decks Upgrading & Skids Installation Barboni-1 ptf.
    • 2008
    • IEPTI
  8. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah North Monopod Jacket Transportation & Installation - Thekah N ptf.
    • 2008
    • IETI
  9. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah North Deck Transportation & Installation - Thekah N ptf.
    • 2008
    • IETI
  10. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah 2 Monopod Jacket Transportation & Installation - Thekah 2 ptf.
    • 2008
    • IETI
  11. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah 2 Monopod Deck Transportation & Installation Thekah 2 ptf.
    • 2008
    • IETI
  12. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah PLEM-1 Base Frame Transportation & Installation
    • 2008
    • IETI
  13. Thekah Gas Field
    • Egypt – Offshore
    • PETROBEL/PMS
    • Thekah PLEM-2 Base Frame Transportaion & Installation
    • 2008
    • IETI
  14. Darfeel Gas Field (Semman Gas Field)
    • PETROBEL/PMS
    • Semman platform Deck and Flare Installation
    • Mediterranean Sea - Offshore Egypt
    • 2007 I
  15. Didon Offshore Oil Field
    • Offshore Tunisia
    • MP ZARAT
    • Didon ptf. Offshore installation of the production jacket, topside drilling and production platform, inst. & hook up
    • 2006
    • IEPI
  16. Temsah Gas Field
    • Egypt
    • PETROBEL CAIRO
    • EIH
    • Hook up activities, PLEM and spools installation on Akhen, Temsah 4 and Barboni Platforms
    • 2005
  17. Miskar Gas Field
    • Tunisia
    • BECHTEL (BG TUNISIA)
    • Miskar ptf. shutdown (preparatory to the installation of the Compression Module)
    • 2003
    • EFIHT
  18. AGIP GAS BV - LIBYAN BRANCH – LIBYA , Installation of pre-drilling Template, Libya, 2002, IHE
  19. NAVALMARE - (ENI-AGIP) , Installation of Davide 7 ptf.; Hiring of personnel during hook-up phases on Davide ptf. and Davide 7 ptf. S. Benedetto del Tronto – Italy, 2002, IH
  20. PETROBRAS Polo Nord Este – Transportation and installation of no. 7 platforms Polo North East – Campos Basin – Brasil 1988 TIC
  21. PETROBRAS Emergency in Enchova platform: support during the fire extinguishing operation and removal of damaged drilling rig Enchova Field - Brasil April/May 1988 D