Summary Information

  • Ownership: Mangalore Refinery & Petrochemicals Ltd
  • Website: http://www.mrpl.co.in/
  • Location: Mangalore, India
  • Capacity:
    • Before: 11.82 million tons/annum & 236,000 bbl/day
    • After: 15.00 million tons/annum & 300,000 bbl/day
  • Nelson Complexity:
  • Project Stage: Completed
  • Expected Completion: 2012
  • Budget: Rs 12412 Crores

The Project

  • Project Type: Expansion & upgrade
  • Project Summary: The refinery is being expanded to 15 million tons capacity It will also have a delayed coker added.
  • Main Contractors:
    • Technip: The contracts cover the design, engineering, supply and installation of fired heaters in four major units of the MRPL refinery
    • Jacobs: Are providing engineering, procurement and construction management consultancy services for a Crude Distillation/Vacuum Distillation (CDU/VDU) project
    • Toyo Engineering India Limited (Toyo India): Engineering, Procurement and Construction contract on Lump Sum Turnkey basis (EPC-LSTK) from Mangalore Refinery and Petrochemicals Ltd. (MRPL) for setting up Balance Of Plant (BOP) of Delayed Coker Unit (DCU).
    • Punj Lloyd: construction of a Petro Fluid Catalytic Cracking (PFCC) Unit
    • Maire Tecnimont: Heavy Coker Gas Oil Hydro-Treating Unit (CHTU)

Refining Units

  • Crude Distillation,
  • Vacuum Distillation,
  • Delayed Coking 60,000 bpd,
  • Petrochemical Fluid Catalytic Cracking unit
  • Heavy Coker Gas Oil Hydro-Treating Unit (CHTU)

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • The project will also enable MRPL to process cheap and highly acidic crudes (opportunity crudes)

Products Produced

  • The project increase the distillate yield by minimizing black oil production and to upgrade entire Diesel to Euro III/ Euro IV grade.

History

  • 2009 - Maire Tecnimont awarded contract for Heavy Coker Gas Oil Hydro-Treating Unit (CHTU)
  • 2012 - The project is completed with successful commissioning of the new units

Other Information

  • The project has been postponed a number of times