Summary Information
- Operator: Statoil
- Country: Norway
- Location: North Sea
- Production start:
- Partners:
- Production licence 501: Lundin petroleum (operator) 40%, Statoil 40%, Maersk oil 20%
- Production licence 265: Statoil (operator) 40%, Petoro 30%, Det norske oljeselskap ASA 20%, Lundin petroleum 10%
- Type: Oil & Gas
- Estimated Reserves: 1.7 billion to 3.0 billion barrels of oil equivalents
- Production Volume: 550,000 - 650,000 barrels of oil equivalents a day when fully developed
Description
- Johan Sverdrup is among the largest oil fields on the Norwegian shelf, and will at peak contribute with 25% of the production from the Norwegian shelf.
- The giant field is expected to start production in late 2019. The field lifetime will be 50 years, with an anticipated plateau production of 550,000-650,000 barrels of oil equivalent/day (boe/d) field capacity
- The discovery is located in 110 metres of water, the reservoir being situated at a depth of 1900 metres
- The field centre in the first phase comprises a process platform, drilling platform, riser platform and living quarter, and has been designed so as to facilitate future development.
- The installations have steel jackets that are linked by bridges.
- The process platform for refining and producing crude oil will weigh 25,000 tons
- The riser platform for transporting the crude oil extracted from the oil well to the process platform will weigh 21,000 tons
- The oil will be transported to the Mongstad terminal in Hordaland county
- The gas will be transported via Statpipe to Kårstø in Rogaland county for processing and transport onward.
- The development is to be powered from shore by a HVDC link
Contractors
- SHI: Construction of the process platform and riser platform
- Transocean: Appraisal drilling
- Aker Solutions:
- Front-end engineering design (FEED) work, as well as an EPma option for the development's first phase
- Engineering and procurement management for the riser and processing platform topsides
- Hook-up work and gangways for the entire field
- Kvaerner and KBR: Construction of the topside for the utility and living quarters platform
- IKM Ocean Design: Infield Pipelines FEED contract
- KONGSBERG: Supply of safety, automation and lifecycle simulation technology
- Kværner Verdal:
- EPC for riser platform jacket
- Steel jacket for the drilling platform
- ABB:
- Design, engineer, supply and commission power supply systems
- Fabrication and installation of two high-voltage power cables
- Baker Hughes: Contract for integrated drilling services
- Odfjell Drilling: Contracts for drilling services
- IKM Ocean Design: EPC contract for the gooseneck spool and retrofit hot-tap tee
- FMC Technologies: Subsea trees, subsea wellheads, manifolds, and control systems integration
- Mitsui: Linepipe fabrication contract for the export pipelines
History
- 2010 - Johan Sverdrup Oil Field discovered
- 2012 - Successful Johan Sverdrup appraisal well drilled
- 2013 - Further appraisals
- 2013 - Aker Solutions wins contract to provide engineering services, procurement and management assistance (EPma)
- 2014 - Concept selection completed
- 2015 - Major contracts awarded
- 2015 - Development plan submitted to government
- 2015 - Development approval granted
Geology
Links
- Successful Johan Sverdrup appraisal well
- Delineation of oil discovery Johan Sverdrup
- Pre-unit agreement for Johan Sverdrup signed
- Completed appraisal well in Johan Sverdrup
- Johan Sverdrup Oil Field, Lundin Petroleum
- Delineation of the 16/2-6 Johan Sverdrup oil discovery – 16/2-16 and 16/2-16 A
- Recommending Mongstad for Johan Sverdrup oil export
- Concept selection for the Johan Sverdrup field early in 2014
- Aker Solutions Wins Johan Sverdrup Framework Contract
- Concept selection for the Johan Sverdrup field
- IKM Ocean Design awarded Johan Sverdrup Infield Pipelines FEED contract
- KONGSBERG selected to supply safety, automation and lifecycle simulation technology for Johan Sverdrup field development
- Johan Sverdrup: The Making of a Giant
- Johan Sverdrup jacket contract award
- Major Johan Sverdrup contract award
- Submitting the development plan for Johan Sverdrup
- ABB wins $155 million order to power large North Sea oilfield
- Rig and drilling contract for Johan Sverdrup
- Statoil awarding contract for utility and living quarters on Johan Sverdrup
- SHI Wins KRW 1.17 trillion Order to Build 2 Offshore Platforms
- Statoil is awarding the contract for integrated drilling services
- Johan Sverdrup development approved
- Contract for Johan Sverdrup drilling platform jacket
- Hot-tap contract on Johan Sverdrup to IKM Ocean Design
- Contract award for Johan Sverdrup power cables
- FMC Technologies Awarded Phase 1 for Statoil's Johan Sverdrup
- Johan Sverdrup pipeline contracts
- Technip awarded fabrication and installation contracts by Statoil for Johan Sverdrup and Oseberg Vestflanken