Summary Information

The Project

  • Project Type: Greenfield Hydroskimming Refinery
  • Project Summary:
  • Main Contractors:
    • KBR will provide FEED and PMS services to develop the process design, layout, integration and optimization of the facility, develop equipment and material specifications, prepare EPC bid packages and develop an estimate for the construction of the refinery.
    • Technicas Reunidas: Execution of the hydrocracker and diesel hydrotreater facilities under two different contracts for the engineering, supply of the equipment and materials, construction of the plants, precommissioning and providing support during commissioning of the units
    • Al-'Ali Al-Ajmi Group, Petrofac Saudi Arabia Ltd., Hyundai Saudi Arabia Ltd., Hanwa Engineering & Construction Corporation, GGC Corporation, Hitachi Plant Technologies Ltd., SK Engineering & Construction
    • Petrofac: Two engineering, procurement and construction (EPC) packages for the tank farms
    • CBI: Subcontractor for the Tanks Farms

Refining Units

  • Atmospheric Distillation
  • Hydrocracker
  • Diesel hydrotreater

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

  • The refinery will process Arabian Heavy and Arabian Medium crudes

Products Produced

  • The refinery will manufacture approximately 75,000 bpd of gasoline, 100,000-160,000 bpd of ultra-low-sulfur diesel (10 parts per million), and 160,000-220,000 bpd of fuel oil

History

  • 2011 - KBR was awarded a contract by Saudi Aramco to provide front-end engineering and design (FEED), and Project Management Services (PMS).
  • 2012 - Saudi Aramco, signed contracts with the representatives of eight local and international construction and procurement companies
  • 2014 - CBI awarded LPG tank contract

Other Information

  • -

Relevant Links

  1. Jizan Refinery and Terminal
  2. Aramco releases tender for USD 7 billion Jizan Refinery
  3. Alderley supply metering systems – Jazan Refinery Project
  4. KBR Awarded FEED and Project Management Services Contract by Saudi Aramco for the Jazan Refinery and Marine Terminal Project
  5. Jazan Project contracts signing
  6. Saudi Aramco selected Técnicas Reunidas for two major refining projects in Saudi Arabia
  7. Petrofac Awarded Two Contracts at Jazan
  8. CB&I Awarded Sphere Storage Contract By Petrofac

Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License