Summary Information

  • Operator: ConocoPhillips
  • Country: UK
  • Location: blocks P011 and P0032 30/7a, Central North Sea
  • Production start: 2013
  • Partners: ConocoPhillips - 36.5, BG Group - 30.5%, ENI - 33.0%
  • Type: Gas And Condensate
  • Estimated Reserves: recoverable reserves are estimated at around 170 mmboe
  • Production Volume:

Description

  • Jasmine is a high pressure, high temperature (HP/HT) gas-condensate reservoir
  • The Jasmine development, located approximately 5.5 miles west of the Judy production facility, comprises a Jasmine wellhead platform (WHP) and an accommodation and utility platform bridge-linked to the WHP; a Judy riser and separation platform (JRP) with additional Judy well slots bridge-linked to the existing Judy platform; and a multiphase pipeline from the WHP to the JRP.
  • From Judy, gas is trasported via the CATS Central Area Transmission System Gas Pipeline to the Teesside Gas Processing Plant TGPP

Contractors

  • Halliburton: Directional drilling, logging-while-drilling (LWD) and surface data logging (SDL) services
  • Dragados Offshore: Constructability analysis, construction engineering, partial purchases, construction, commissioning, load out and sea fastening of two decks
  • WorleyParsons: Detailed engineering for three platforms, interconnecting bridges, pipe-in-pipe risers and spools along with the functional design and specification for the subsea pipeline, subsea isolation valves, power/communications cable and umbilicals
  • Subsea 7: Engineering, procurement, fabrication, installation and commissioning of two approximately 4km pipeline bundle systems and associated pipe-in-pipe spools
  • AMEC: Detailed engineering and procurement the existing Judy platform and the hook-up and commissioning of their new Jasmine facilities
  • Rosetti Marino:
    • Procurement, Construction and Commissioning of Topsides for the Jasmine platform
    • Construction engineering, procurement, fabrication, load-out and sea-fastening of JASMINE WHP, JLQ & JRP substructures
  • IKM Testing: Pressure Tests, Bolt Tensioning & Torquing, Hot Oil Flushing, Cleaning, Video Inspection, Test Engineering, Drying & N2 Purging
  • Saipem: Wellhead, accomodation and process platforms
  • FoundOcean: Grouting for Jasmine Living Quarters & WHP
  • KWSubsea: Pipeline Concept Engineering Services

History

  • 2006 - Jasmine Gas And Condensate Field discovered
  • 2010 - WorleyParsons awarded Detailed engineering contract
  • 2010 - Halliburton awarded drilling contract
  • 2010 - Dragados Offshore awarded deck contract
  • 2013 - First gas produced

Geology

Links

  1. Central North Sea, ConocoPhillips
  2. List Of Oil and Gas Production Platforms In The UK
  3. Saipem Fixed Offshore Production Facilities Project References
  4. FoundOcean Subsea References
  5. KWSubsea Subsea References
  6. Rosetti Marino Platform References
  7. BG Group announce substantial North Sea discovery
  8. Subsea 7 Confirms Contract for ConocoPhillips Jasmine Discovery in the North Sea
  9. IKM Testing Spain awarded a new contract
  10. Halliburton Wins Contract for Jasmine
  11. Award by ConocoPhillips for Jasmine Area Development
  12. AMEC awarded Judy and Jasmine contract North Sea
  13. Conocophilips Awards A New Contract To Dragados Offshore
  14. First gas production from UK Jasmine field

Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License