Irpc Rayong Refinery
Summary Information
- Ownership: IRPC
- Website: http://www.irpc.co.th/
- Location: Rayong, Thailand
- Capacity: 10.75 million tons/annum & 215,000 bbl/day
- Nelson Complexity:
- Refining Depth:
Brief Description
- -
Refining Units
- Atmospheric Distillation 65,000 + 150,000
- Lube base plant - 320,000 tons per annum
- Asphalt plant - 380,000 tons per annum
Terminal Capacity
- Crude Oil:
- Refined Products:
Crude Supply
- The refinery processes condensate as well as crude
Products Produced
- Gasoline, diesel and LPG
Ongoing Projects
- See IRPC Rayong Refinery Upgrade Project
- A 30,000 barrels per day deep catalytic cracking (DCC) unit is being constructed
- The refinery is adding a Tail Gas Treating Unit 1 and Amine Regeneration Unit 2
Other Information
- -
History
- 2011 - Euro 4 Petrol launched
- 2011 - Fuel oil usage was eliminated with the CHP unit commissioned
- 2012 - Shaw awarded contract for DCC Unit
Relevant Links