Drydocks World FPSO References
- Client: Saipem Energy Services SpA
- Project: Tanker Betatank II to Firenze FPSO
- Project Status: Ongoing
- Client: Saipem SpA for Sonangol
- Project: VLCC Magdeline to Gimboa FPSO
- Project Duration: July 2006 - September 2008
- Client: Saipem SpA for Petrobras
- Project: VLCC Margaux to Cidade De Vitoria FPSO
- Project Duration: July 2005 - June 2007
- Client: SBM IMODCO for Chevron
- Project: VLCC Lu San to Frade FPSO
- Project Duration: December 2006 - January 2009
- Client: SBM Offshore N.V. and Sonangol for Exxon Mobil Corporation
- Project: VLCC Mosocean into Xikomba FPSO
- Project Status: Project completed in 2003
- Client: Single Buoy Moorings Inc.
- Project: Conventional VLCC to FPSO Atlantic
- Project Duration: 2002 - 2003
- Client: Single Buoy Moorings Inc.
- Project: Conventional Crude Carrier Stena Contender to FSO Nkossa1
- Project Year: 1996
- Client: Saipem, ENI/Single Buoy Moorings Inc.
- Project: Conventional medium size crude tanker to Mystras FPSO II
- Project Duration: 2002 - 2003
- Client: Fred Olsen Production AS for Canadian Natural Resources Limited
- Project: VLCC to Knock Allan FPSO
- Project Duration: September 2007 – December 2008
- Client: Fred Olsen Production A.S. for Addax Petroleum and Sinopec
- Project: VLCC Elgreco to Knock Adoon FPSO
- Project Duration: 2005 - 2006
- Client: FPSOcean
- Project: Shuttle tanker to FPSO Deep Producer I
- Project Duration: March 2007 to January 2009
page revision: 12, last edited: 09 Oct 2015 07:59