Summary Information
- Operator: Quadrant Energy
- Country: Australia
- Location: 80km northwest of the port of Dampier
- Production start: 2011
- Partners: Santos
- Type: Gas
- Estimated Reserves: The Reindeer field proven and probable (2P) reserves are estimated at approximately 485 Petajoules of sales gas and 1.6 million barrels of condensate.
- Production Volume:
Description
- The development consists of an offshore gas field, Reindeer and an onshore gas processing plant, Devil Creek
- Reindeer gas is produced via an unmanned, minimum facility wellhead platform located in 65 metres of water
- The WHP is a four leg jacket with one skirt pile per leg and four level topsides with an integrated helideck location on the upper deck. A single 406 mm (16”) subsea and offshore gas pipeline links the WHP to an onshore gas treatment plant (the Devil Creek Gas Plant).
- The raw natural gas will be processed and then supplied into the Dampier To Bunbury Natural Gas Pipeline. A second commercial product derived from the gas stream will be condensate. Devil Creek will initially provide up to 110 Terajoules (TJ/d) per day for the Western Australian domestic gas market and has been designed to process up to 220 TJ/d of natural gas
Contractors
- Shenzhen Chiwan Sembawang Engineering: Fabrication of wellhead platform
- SapuraAcergy: Transportation and installation of approximately 91km of 16” rigid pipeline including a shallow water beach approach, subsea tie-in and stabilisation works together with a wellhead platform of a 1,700T four leg jacket and a 450T topside processing module
- John Holland: Contract for construction of onshore facilities
- Clough: Engineering, Procurement and Fabrication of the onshore gas plant
- FoundOcean: Grouting
History
- 1997 - Reindeer Gas Field discovered
- 2007 - Commencement of FEED
- 2008 - Reindeer Project Sanctioned
- 2009 - SapuraAcergy awarded offshore contract
- 2009 - Groundbreaking ceremony for gas processing plant
- 2011 - First gas from Reindeer / Devil Creek
- 2015 - Quadrant Energy acquired Apache's share
Geology
- Middle Jurassic Legendre Formation
Links
- Reindeer Wellhead Platform and Offshore Gas Supply Pipeline Operations Environment Plan Summary
- FoundOcean Subsea References
- Shenzhen Chiwan Sembawang Engineering Platform References
- Reindeer 1
- Commencement of FEED for Reindeer Field
- Reindeer Project Sanctioned
- Award for $170 million Offshore Australia contract to SapuraAcergy Joint Venture
- Reindeer Project Update
- First gas from Reindeer / Devil Creek
- Groundbreaking signals commencement of new WA domestic gas hub
- John Holland, Project page
- John Holland to deliver Devil Creek development project for Apache Energy Limited
- Apache Agrees To Sell Australian Operations For $2.1 Billion
page revision: 17, last edited: 04 Sep 2015 13:54