Derescom Oil And Gas Processing References
Related Pages
Engineering News
Engineering Blog Entries
Most Recently Updated Pages
Probably the most exciting project in the world of Oil & Gas. The platform will be the largest ship ever built
- Poinsettia Gas Field
- Trinidad
- BG Group / Fluor
- Fuel Gas Treatment/Pressure Reduction Package
- 2007
- fixed offshore platform
- Thunder Hawk Oil And Gas Field
- USA
- SBM Offshore
- Glycol regeneration package, 60mmscfd, 1,960psig operating pressure
- 2007
- floating production (spar)
- Khalda Petroleum / Petrofac Egypt Salem Gas Train Glycol dehydration packages for sales gas trains 2007, On shore
- North Oil Company Iraq Khurmala Dome Two electrostatic treaters and four crude heaters 2006, onshore
- North Oil Company Iraq Khurmala Dome Design and supply of 100 MMSCFD Glycol Dehydration and Regeneration Unit 2006, onshore
- Pemex Exploration and Production Mexico Sinan C and D Platforms Two 48” x 15’ x 1800 psig horizontal test separators
- Total / Fina / Elf US GoM Matterhorn TLP Replacement grid package for 120” x 40’ electrostatic treater, 2005, floating production, TLP
- Pemex Exploration and Production Mexico Sinan A Platform 48” x 15’ x 1800 psig horizontal test separator package 2005, Fixed offshore platform
- Pemex Exploration and Production Mexico Sinan A Platform HP/LP fuel gas conditioning package 2005, Fixed offshore platform
- Pemex Exploration and Production Mexico Sinan B Platform 48” x 15’ x 1800 psig horizontal test separator package 2005, Fixed offshore platform
- Pemex Exploration and Production Mexico Sinan B Platform HP/LP fuel gas conditioning package2005, Fixed offshore platform
- Trinidad Exploration and Production Onshore Trinidad 26” x 10’ x 1440 psig horizontal test separator package 2005, onshore
- El Paso Energy Onshore USA Two indirect line heaters, 1.5 MMBTU/HR each 2004 ohshore
- Pearl Oil c/o Expro Indonesia Indonesia 120” x 40” x 150 psig electrostatic heater treater. Scope included design, supply of internals, transformers, and burners, 2005 fixed offshore platform
- AGOCO Libya Sarir Six slot manifold, 2005, onshore
- Newfield Exploration and Production Offshore USA 96” x 20’ x 150 psig horizontal water skimmer package 2005, fixed offshore platform
- Shell Oil Offshore USA Auger Platform 120’ x 30’ x 250 psig horizontal electrostatic bulk oil treater, 2006 floating production, TLP
- Xplor Energy Offshore USA Main Pass 35 Repair and startup of glycol dehydration package 2005, fixed offshore platform
- Chevron Offshore Angola Design of 120” x 40’ x 500 psig vertical deareator vessel 2006, fixed offshore platform
- W.G. Helis Offshore USA West Cameron Block 21 Packages included 36” x 10’ x 1440 psig Test Separator, 48” x 10’ x 1440 psig production separator, 72” x 20’ x 125 psig water skimmer, 20 mmscfd glycol dehydration package 2004 fixed offshore platform
- British Gas c/o Worley Parsons Limited Offshore Trinidad Central Block facility Fuel Gas Treatment/Pressure Reduction Package 2006, fixed offshore platform
- Shell Oil McAllen Gas Plant 250 MMSCFD pressurized reconcentrator, gas inlet saturated at 1000 psig and 115oF, outlet requirement 6 LBS/MM 1999, onshore
- Bay Gas Storage Onshore USA 300 MMSCFD, Mobile, Alabama - Storage dome facility, gas inlet under saturated at 1000 psig and 120oF, outlet requirement 6 LBS/MMs , 1998 - onshore
- Petrobras, Project P-36 Semi-submersible 250 MMSCFD gas inlet saturated at 2500 psig and 120oF, outlet requirement 3 LBS/MM 1997 – floating production, TLP
- ExxonMobil East Cameron Block 286 Glycol dehydration unit, 100 MMSCFD gas inlet saturated at 1100 psig and 120oF, outlet requirement 7 LBS/MM 1996, fixed offshore
- BP USA GoM Marlin facility Glycol dehydration package, 300 MMSCFD TLP in Gulf of Mexico. Design to allow increasing capacity by 50% while eliminating operating problems 1999, Floating Production, TLP
- Chevron Nigeria Escravos Glycol Dehydration unit, one 200 MMSCFD Unit and one 50 MM unit. Designs to increase capacities of both. 1998, inshore waters, fixed paltform
- Duke Energy USA Moss Bluff Glycol dehydration unit One 1000 MMSCFD unit - complete new reconcentrator and replacement of bubble cap trays with structured packing to increase capacity and reduce glycol losses. 1998, onshore
- Newfield Exploration and Production USA Brazos 504B 15 MMSCFD facility, tripod deck, jacket and piles 2004, fixed offshore
- Mariner Energy West Cameron 333 20 MMSCFD w/associated liquids facility, deck, jacket and piles 2004, fixed offshore
- Tana Exploration USA Brazos A2B 10 MMSCFD facility, tripod deck jacket and piles, 2003 fixed offshore
- Saipem Angola West Espoir Field Test Separator, Pig Launcher, and Vent Scrubber Packages, 2004, fixed offshore
- Occidental Petroleum Ecuador Two (2) 10’ x 50’ bulk oil separators, 2004, onshore
- Dominion E & P USA Fabrication of 50/100 MMSCFD standard gas processing module, 2002, fixed offshore platform
- Dominion E & P USA Refurbishment of 100 MMSCFD standard gas processing module, 2002, fixed offshore platform
- McDermott / Spartec USA Design and Fabrication of major process equipment for the Front Runner, Devils Tower, and Medusa deep water spars, 2001 floating production, Spar
- ExxonMobil Nigeria Yoho project Design and fabrication of the process equipment for the phase A development project, 2002 fixed offshore platform
- Williams Energy USA Canyon Express Designed and Constructed separation, water treatment, and oil treating packages 2002, fixed offshore platform
- ExxonMobil Angola Kizomba “A” Fabrication of oil treating and seawater deairating equipment, 2003, FPSO
- Petrobras / Mannesman Demag Brazil Ubarana Project Four-train gas turbo-compressor plant, process packages and interconnect piping, design, fabrication, hookup and commissioning 1997, onshore
- CMS Nomeco / Global Industries Equatorial Guinea Alba Field Development Twelve oil and gas process packages, featuring Incoloy clad vessels, design, fabrication and pre-commissioning 1998 fixed offshore
- Murphy E & P USA GoM Eugene Island 335A Oil production modules including separation and water treatment facilities for 1500 bopd and associated gas, design, fabrication and pre-commissioning 1998, fixed offshore
- Chevron / W & T Offshore Main Pass 29 Oil dehydration and treating facilities, design, fabrication, hookup and commissioning, 1998 fixed offshore platform
- Coastal Oil and Gas Vermilion 250H Oil treatment package, design, fabrication and pre-commissioning, 1999 fixed offshore platform
- Murphy E & P USA GoM South Timbalier 63A Complete oil process facilities with nominal liquids and gas, design, fabrication and pre-commissioning, 1999,. Fixed offshore platform