Summary Information
- Ownership: Cosmo Oil
- Website: http://www.cosmo-oil.co.jp/
- Location: Chiba, Japan
- Capacity: 11.0 million tons/annum & 220,000 bbl/day
- Nelson Complexity:
- Refining Depth:
Refining Units
- Atmospheric Distillation 110,000 bpd + 130,000 bpd
- Vacuum Distillation Unit 20,000 bpd + 60,000 bpd
- Prefractionator Unit 23,000 bpd
- Catalytic Reforming Unit 11,500 bpd + 25,000 bpd
- Reformate Splitter 9,000 bpd + 20,000 bpd
- Fluid Catalytic Cracking Unit 40,000 bpd
- FCC Gasoline Hydrodesulfurization Unit 24,000 bpd
- Hydrodesulfurization Units 8,000 bpd + 26,000 bpd + 55,000 bpd + 50,000 bpd
- Isomerization Unit 6,000 bpd
- Vacuum Gas Oil Hydrodesulfurization Unit 35,000 bpd
- Hydrogen Recovery by Membranes Separation System Unit 331,200 m³N / day
- Fuel Oil Hydrodesulfurization Unit 36,000 bpd + 36,000 bpd
- No.1 Hydrogen Producing Unit 648,000 m³N / day
- No.10·20 Hydrogen Producing Unit 880,000 m³N / day × 2
- Sulfur Recovery Unit(With Tail Gas Treating Unit) 150 t / day × 3
- Blown Asphalt Unit 3,600 t / month
Terminal Capacity
- Crude Oil: (13units) 930,000kl
- Finished Product /Semi-processed Product Tanks (119units) 1,490,000kl
- Lubricating Oil Tanks (66units) 24,000kl
- Sulfur Tanks (2units) 13,200kl
- Asphalt Tanks (20units) 28,000kl
- LPG Tanks (23units) 52,700kl
Crude Supply
- -
Products Produced
- LPG, Gasoline, Diesel, Jet Fuel, Fuel Oil, Asphalt, Sulphur
Ongoing Projects
- -
Other Information
- -
History
- 1963 - Refinery commissioned
- 2006 - Fire and explosion in the desulfurization unit
- 2010 - Nameplate capacity reduced by 20,000 to 220,000 bbl/day
- 2011 - Refinery fire occurs after an earthquake
- 2012 - Restart of CDU damaged in the fire
Relevant Links
- Refinery Webpage
- Japanese Refining Capacities
- Reduction of CDU Nameplate Capacity
- Preparations for Start-Up of Crude Distillation Unit (CDU) at Chiba Refinery
- Start-Up of Crude Distillation Unit (CDU) at Chiba Refinery
- Preparations to Resume Operation of the #1 CDU at Chiba Refinery Following Completion of the Safety Inspection
page revision: 16, last edited: 20 Apr 2012 08:10